Meeting went well with the fire marshal. They agreed to the following timeline:
2013: Remodel/add preschool
2014: Gather gifts
2015: Bring new sprinkler water service to building
2016: install sprinklers in basement.
2017: install sprinklers in upstairs
We have a lot of work to do in remodeling the classroom and there are
still some hurdles we have to get past before we are "swinging hammers".
Please consider volunteering to help when the time comes and keep this
project in your prayers.
Praise The Lord!
Channing Lillo